OnAugust 3, 2016,thedredgingproject ofoilterminal in Namibiacontracted andconstructed by TDCsuccessfullycompleted, which is 90 days before theschedule.
Thetotal dredging volume of this project accounts for about 6.89M m³.The site containsnumerous hydrogen sulfide, which ispoisonous,flammable and combustible. TDC overcame difficulties and took measures to guarantee thesafety construction of the project.Tong Li finished the taskahead of schedule with theconstruction period of 403 days,during which nopoisoning incident occurred.
Copyright Reserved © 2013 CCCC Tianjin Dredging Co.,Ltd.